Phase V has been approved.

Posted by Jim Bresnahan on March 1, 2019 at 10:20 PM

Phase V will be built with funds provided bt the Missouri Clean Water Fund. GASD will receive a loan of $1.635 million with a matching grant of $1.635 million. Approximately $600,000 will be spent to expand the sewer plant to be better able to handle the heavy summer flow of sewage. The District plans to implement sewers in a portion of Pistol Point off of Highway O, the rest of Moffitt Point, Morgan Hills, and King Road. Paperwork is currently underway.