Sewer Construction Update

Posted by Jim Bresnahan on January 5, 2012 at 8:40 AM

Ridge Hill Contractors (contract 2 & 3) have indicated that they will be starting in the Tony's Point area , Eastwood, and Morning Sun first. The collection pipes will be going in first in these areas. Rosetta Construction (contract 1) has been stockpiling pipe and plans to be clearing brush South of Troutdale Rd. in Gravois Mills first.

Categories: None

Post a Comment

Oops!

Oops, you forgot something.

Oops!

The words you entered did not match the given text. Please try again.

Already a member? Sign In

1 Comment

Reply Jamie Christie
4:24 PM on January 11, 2012 
Ridge Hill started digging in Eastwood on January 9th and in Morning Sun on January 11th. In Morning Sun, they are going down the hill and around the inside of the circle road for this phase of digging.