April 3, 2012 Update

Posted by Jim Bresnahan on April 3, 2012 at 12:35 PM

The weather continues to be favorable for construction of Phase 3. As of April 2, contracts 2 and 3 have laid 54,000 feet of force main and 1600 feet of gravity main. Approximately 25 grinder tanks are in place and electricians are installing control panels and disconnects. Rosetta Construction is nearing 5-18 from the North and is presently preparing the ditch from Coconuts to March Rd. The force main from 5-18 south to the plant is in. We would like to remind homeowners that final grade work around grinders has not begun. Donna Swall, Director of LOWA, presented a program that may be of interest to homeowners at the monthly GASD meeting last night. LOWA has a program of Low Impact Landscaping, (LIL). The program deals with gardens and buffer strips that help control water runoff. There are cost sharing incentives and discounts available that may be of interest. Please check out the LOWA web site at www.sosLOWA.org for further information. Dave Taylor, Chairman, GASD

Categories: None

Post a Comment

Oops!

Oops, you forgot something.

Oops!

The words you entered did not match the given text. Please try again.

Already a member? Sign In

1 Comment

Reply Dave
1:11 PM on May 9, 2012 
Please let me know what money residents of Phase 3 are required to pay before connecting to the system.

Join Our Site

Get News & Updates

Your E-Mail is Kept Private!

Click Here

LOWA Web Site